Comment
Draft Black Country Plan
Representation ID: 22489
Received: 11/10/2021
Respondent: South Staffordshire Council, Planning and Strategic Services
Appendix 2 – South Staffordshire comments on Walsall Green Belt site delivery [table] [See attachment]
[Table headers:] Site Reference/Address/Claimed delivery
potential (Black Country)/Estimated delivery potential (South Staffordshire)/Comments [appear below these]
WAH232 Yieldsfield Farm
(sometimes recorded as
Yieldfields farm), Stafford
Road, Bloxwich
978 (600 dwellings
by 2039)
978 by 2037 This is based on the plan being adopted in 2024 and the following assumptions set out in
paragraphs 4.55 – 4.69 of the Black Country Plan Viability and Delivery Study (May 2021):
- Build commencement 2028 (4 years max. lead-in time)
- 100 dpa build rate
WAH234 Land between Queslett
Road, Doe Bank Lane and
Aldridge Road, Pheasey
1426 (960 dwellings
by 2039)
1426 dwellings by
2039
This is based on the plan being adopted in 2024 and the following assumptions set out in
paragraphs 4.55 – 4.69 of the Black Country Plan Viability and Delivery Study (May 2021):
- Build commencement 2028 (4 years max. lead-in time)
- 100 – 200 dpa build rate on sites significantly above 500 dwellings (implying a maximum potential
capacity of between 1,200 – 2,400 dwellings up to 2039)
Based on the above assumptions, the site only needs to achieve a 118 dpa build rate to be delivered
fully in the plan period. Given the site’s size and the recommended range of 100 – 200 dpa given in
the May 2021 report for such sites, it seems realistic to assume the site will be completed within the
plan period.
WAH235 Home Farm, Sandhills,
Walsall Wood
1417 (800 dwellings
by 2039)
1417 dwellings by
2039
This is based on the plan being adopted in 2024 and the following assumptions set out in
paragraphs 4.55 – 4.69 of the Black Country Plan Viability and Delivery Study (May 2021):
- Build commencement 2028 (4 years max. lead-in time)
- 100 – 200 dpa build rate on sites significantly above 500 dwellings (implying a maximum potential
capacity of between 1,200 – 2,400 dwellings up to 2039 on large sites in the Black Country)
Based on the above assumptions, the site only needs to achieve a 118 dpa build rate to be delivered
fully in the plan period. Given the site’s size and the recommended range of 100 – 200 dpa given in
the May 2021 report for such sites, it seems realistic to assume the site will be completed within the
plan period.
WAH238 Land at Vicarage Road /
Coronation Road, High
Heath
504 (400 dwellings
by 2039)
504 dwellings by
2035/36
This is based on the plan being adopted in 2024 and the following assumptions set out in
paragraphs 4.55 – 4.69 of the Black Country Plan Viability and Delivery Study (May 2021):
- Build commencement 2028 (3 years lead-in time, reflecting greenfield site)
- 50 - 60 dpa build rate (assuming one outlet)
WAH242 Calderfields West,
Aldridge Road, Walsall
592 (442 dwellings
by 2039)
592 dwellings by
2036 - 2038
This is based on the plan being adopted in 2024 and the following assumptions set out in
paragraphs 4.55 – 4.69 of the Black Country Plan Viability and Delivery Study (May 2021):
- Build commencement 2028 (3 years lead-in time, reflecting greenfield site)
- 50 - 60 dpa build rate (assuming one outlet)