Comment

Draft Black Country Plan

Representation ID: 21260

Received: 11/10/2021

Respondent: Redrow Homes Ltd

Agent: Savills

Representation Summary:

Policy DEL1 – Infrastructure Provision
Policy DEL1 states that all new developments should be supported by the necessary on and off-site infrastructure. It is currently unclear what level of infrastructure is required to support Strategic Allocation WSA2 and whether this is required on-site or as an off-site contribution. The Viability and Deliverability Study (May 2021) states that no health or education input has been received for Walsall. Point 3 of the policy states that further detail will be provided by the BCA to confirm what level of infrastructure should be provided. We consider that this is required in order to ascertain what level of contribution is required for Strategic Site WSA2.