Black Country Core Strategy Issue and Option Report

Question 1 - Do you agree that the Core Strategy review should be a partial review, retaining and stretching the existing spatial strategy and updating existing policies? Yes/No; If not, what do you

Representation ID: 1003

Received: 23/10/2017

Respondent: Hallam Land Management

Agent: Acres Land & Planning Limited

Representation Summary:

We broadly support the need for a partial review, retaining the basis of the existing Core Strategy - Hallam Land do not wish to prolong the exercise by starting entirely afresh and re-inventing those aspects of the planning strategy which already work effectively - but we do feel the review needs to be sufficiently far-reaching to challenge the current Core Strategy and to test its robustness thoroughly and also to reflect the changes in policy approach since the NPPF was introduced.

Comment

Black Country Core Strategy Issue and Option Report

Question 2 - Do you think that the key evidence set out in Table 1 is sufficient to support the key stages of the Core Strategy review? Yes/No; If not, what further evidence is required and, if there

Representation ID: 1004

Received: 23/10/2017

Respondent: Hallam Land Management

Agent: Acres Land & Planning Limited

Representation Summary:

Hallam Land acknowledges the list of strategic challenges and opportunities identified as 'Key Issues' in paragraph 3.1 of the Core Strategy document.

Comment

Black Country Core Strategy Issue and Option Report

Question 3 - Do you agree that the housing need identified for the Black Country over the period 2014-36 in the SHMA, and the anticipated amount of supply, are appropriate and in line with national gu

Representation ID: 1006

Received: 23/10/2017

Respondent: Hallam Land Management

Agent: Acres Land & Planning Limited

Representation Summary:

The assessment of housing need in the Black Country is extremely complicated, since it is surrounded by local authorities on all sides. The Housing White Paper advocates a standardised approach to housing needs assessment which should narrow the areas for debate in settling OAN (Objectively Assessment Need) figures. This may work where housing markets are relatively self-contained with identifiable economic and housing catchment areas - but this is clearly not the case for the Black Country.

Comment

Black Country Core Strategy Issue and Option Report

Question 4 - Do you consider the employment land requirement identified for the Black Country up to 2036 in the EDNA is appropriate and in line with national guidance? Yes/No; If not, please explain w

Representation ID: 1008

Received: 23/10/2017

Respondent: Hallam Land Management

Agent: Acres Land & Planning Limited

Representation Summary:

The nature of the economy has changed significantly over the last 10-15 years. Although the Black Country is the traditional home to extractive industries, manufacturing and especially metal-bashing much of this heavy industry has moved to other countries to be replaced by higher value manufacturing and services - including distribution. At the other end of the scale, the economy now encourages smaller-scale initiatives with a sharp rise in small businesses and self-employment.

It is therefore much more difficult to gauge the employment land requirements since the more traditional industrial estate forms only a partial element of employment needs. Employment may also be transient and not necessarily place-based. Recent history has shown that there is a pressing need for readily available large employment sites to meet the one-off inward investment such as JLR which tends to create large numbers of jobs, both in direct and spin-off employment. Similarly, distribution now requires much larger loading bays with high spans which can accommodate the needs of the current market. The West Midlands Strategic Employment Sites Study and the Black Country & South Staffs Sub-Regional High-Quality Employment Land Study will provide an important part of the evidence base.
We therefore support the portfolio approach to the provision of employment sites.

Comment

Black Country Core Strategy Issue and Option Report

Key Issue 5 - Protecting and enhancing the environment

Representation ID: 1009

Received: 23/10/2017

Respondent: Hallam Land Management

Agent: Acres Land & Planning Limited

Representation Summary:

It is self-evident that planning policies should be devised to protect the environment and to avoid damage to Special Protection Areas (SPA's), RAMSAR sites, water quality and other aspects of the natural environment.

Support

Black Country Core Strategy Issue and Option Report

Question 5 - Do you agree with the proposed approach to the Black Country Green Belt Review? Yes/No; If not, what additional work do you think is necessary?

Representation ID: 1010

Received: 23/10/2017

Respondent: Hallam Land Management

Agent: Acres Land & Planning Limited

Representation Summary:

We welcome the recognition that the implications of future growth in and around the Black Country will require a systematic review of the Black Country green belt and that this will be done in a consistent way with the other local authorities in the Birmingham and Black Country housing market area. The emerging Greater Birmingham and Black Country HMA Strategic Growth Study, being produced by GL Hearn provides the right context for the Black Country Green Belt review and it is logical (as suggested in paragraph 3.47) that this should also cover the South Staffordshire area which falls into the same general housing market area and maintains strong economic links.

Support

Black Country Core Strategy Issue and Option Report

Question 6 - Do you agree that the key issues set out in Part 3 are the key issues that need to be taken into account through the Core Strategy Review? Yes/No; If not, what other key issues should be

Representation ID: 1011

Received: 23/10/2017

Respondent: Hallam Land Management

Agent: Acres Land & Planning Limited

Representation Summary:

We agree that, subject to the caveats wish we have listed above, these key issues outlined in Part 3 represent the factors which need to be taken into account through the Core Strategy.

The key issues outlined in paragraph 3.1 are as follows:

* Updating the evidence base
* Meeting the housing needs of a growing population
* Supporting a resurgent economy
* Supporting strong and competitive centres
* Protecting and enhancing the environment
* Reviewing the role and extent of the green belt
* Keeping the Black Country connected
* Providing infrastructure to support growth
* Working effectively with neighbours.

Support

Black Country Core Strategy Issue and Option Report

Question 7 - Do you think that the Core Strategy vision and sustainability principles remain appropriate? Yes/No; If not, what alternatives would you suggest?

Representation ID: 1012

Received: 23/10/2017

Respondent: Hallam Land Management

Agent: Acres Land & Planning Limited

Representation Summary:

Yes. We broadly support the Core Strategy Vision and sustainability principles. However, although we accept that ideally it may be desirable to 'put brownfield first' in terms of the authorities' priorities, in practical terms this is not always feasible. In any event, a 'brownfield first' strategy for housing is not actually Government policy. Authorities are expected to encourage and promote the development of brownfield sites for housing but this may not necessarily mean putting brownfield before greenfield development. The market would grind to a halt if they did so.

Comment

Black Country Core Strategy Issue and Option Report

Question 8 - Do you think that the Core Strategy spatial objectives remain appropriate? Yes/No; If not, what alternatives would you suggest and how might these changes impact on individual Core Strate

Representation ID: 1013

Received: 23/10/2017

Respondent: Hallam Land Management

Agent: Acres Land & Planning Limited

Representation Summary:

The 10 objectives seem broadly sound as a basis for planning and regeneration of the review period. However, although there is a mention of existing housing areas in Objective 4, there is no actual reference to providing an adequate level of new housing, in places where people want to live. Furthermore, the Objective 3 which refers to 'Model sustainable communities on redundant employment land in the Regeneration Areas' does not reflect the change in stance within the review which will now be looking at a wider portfolio of sites, including some Green belt sites both with the Black Country and South Staffordshire. There is also no reference to working in partnership with neighbouring authorities or the private sector, something which is essential to achieve delivery.

Support

Black Country Core Strategy Issue and Option Report

Question 9 - Do you agree that Policies CSP1 and CSP2 should be retained and updated to reflect new evidence and growth proposals outside the Growth Network? Yes/No; If not, what changes do you think

Representation ID: 1014

Received: 23/10/2017

Respondent: Hallam Land Management

Agent: Acres Land & Planning Limited

Representation Summary:

Yes. We agree that policies CSP1 and SP2 remain relevant. But they may be rather too prescriptive in trying to direct development to specific centres, locations and corridors. The Review provides the opportunity to gauge to what extent the current Core Strategy has succeeded both in focusing development on preferred locations but more important in boosting and regenerating the Black Country. These policies may have unintended consequences if they tend to deflect growth elsewhere.