Black Country Core Strategy Issue and Option Report

Search representations

Results for IM Land search

New search New search

Comment

Black Country Core Strategy Issue and Option Report

Question 12a - Do you support Spatial Option H1? Yes/No; What criteria should be used to select suitable sites? e.g. ability to create a defensible new green belt boundary, size, access to existing re

Representation ID: 1489

Received: 08/09/2017

Respondent: IM Land

Agent: Turley Associates

Representation Summary:

Please refer to response to Question 13a.

Attachments:

Comment

Black Country Core Strategy Issue and Option Report

Question 13a - Do you support Spatial Option H2? Yes/No; What should the characteristics of Sustainable Urban Areas (SUEs) be? e.g. minimum/ maximum size, mix of uses, mix of housing types, accessibi

Representation ID: 1490

Received: 08/09/2017

Respondent: IM Land

Agent: Turley Associates

Representation Summary:

The BCCS Review should also not make assumptions that SUEs will have major impacts on Green Belt purposes and environmental assets (as suggested in the 'challenges' section for Spatial Option H2). Firstly, any site's performance against the Green Belt purposes is separate to any site selection process. The Green Belt Review is a separate exercise to determining the sustainability of a site. Secondly, SUEs in the Green Belt can have many environmental benefits, including delivering significant public open space (it is widely recognised the Black Country Green Belt is largely inaccessible), as well as biodiversity enhancements.

Attachments:

Comment

Black Country Core Strategy Issue and Option Report

Question 13b - What infrastructure do you think would be needed for different sizes of SUEs?

Representation ID: 1491

Received: 08/09/2017

Respondent: IM Land

Agent: Turley Associates

Representation Summary:

For the reasons provided in response to Q12a and Q13a, further evidence will be necessary to inform infrastructure requirements for each SUE, including school and healthcare provision. The I&O Report indicates a number of infrastructure assessments are to be undertaken before the Preferred Options version of the BCCS Review is published.

Attachments:

Comment

Black Country Core Strategy Issue and Option Report

Question 13c - Are there any potential locations that should be considered for SUEs (please submit through the 'call for sites' form) and what infrastructure would be required to support these?

Representation ID: 1492

Received: 08/09/2017

Respondent: IM Land

Agent: Turley Associates

Representation Summary:

Columba Park represents a unique opportunity to create a new community, which could provide approximately 1,500 new homes. IM's aspirations are to create a new neighbourhood which delivers real health and wellbeing, and economic benefits for both existing and new residents. This includes significant high quality open space, parkland and green infrastructure, well designed homes, and new community facilities.

Attachments:

Comment

Black Country Core Strategy Issue and Option Report

Question 13d - Do you think that the Core Strategy should set out detailed guidance for the development of SUEs (e.g. type and tenure of housing, specific infrastructure required), rather than details

Representation ID: 1493

Received: 08/09/2017

Respondent: IM Land

Agent: Turley Associates

Representation Summary:

Any guidance for SUEs should not be considered until later in the preparation of the Plan, and should be informed by the relevant evidence base (including site specific evidence, the SHMA, and infrastructure assessments). Any guidance should be flexible to ensure the Plan is able to respond to the most up to date evidence.

Attachments:

Object

Black Country Core Strategy Issue and Option Report

Question 15a - If all housing need cannot be met within the Black Country, do you support the 'export' of housing growth to neighbouring authorities within the HMA? Yes/No; What factors should be tak

Representation ID: 1494

Received: 08/09/2017

Respondent: IM Land

Agent: Turley Associates

Representation Summary:

The NPPG is clear that local planning authorities should have fully explored all available options for delivering their housing and employment needs within their own boundaries before considering exporting growth to neighbouring authorities or the wider HMA.

Equally, neighbouring authorities will not accept accommodating any of the Black Country's needs if this exercise has not been thoroughly undertaken. Telford and Wrekin has so far declined to assist in meeting any of the Black Country's shortfall given this exercise had not been undertaken. As such this option should only be considered as a last resort.

On this basis the Black Country should be seeking to accommodate all of its proposed growth within its own boundaries.

Attachments:

Comment

Black Country Core Strategy Issue and Option Report

Question 21 - Do you think that changes are required to Policy DEL1 to ensure it covers both development within the existing urban area and any within the Green Belt? Yes/No; If yes, please provide de

Representation ID: 1495

Received: 08/09/2017

Respondent: IM Land

Agent: Turley Associates

Representation Summary:

As set out in our response to Q1 a full review of the BCCS is necessary. This applies to Policy DEL1 also, particularly as the policy currently only reflects development within the urban area.

Given the characteristics and viability matters which differ between brownfield and greenfield sites, the BCCS Review should have separate policies for each.

Attachments:

Comment

Black Country Core Strategy Issue and Option Report

Question 25 - Will there be any new social infrastructure requirements necessary to serve large new housing developments? Yes/No; If yes, please explain the type and scale of any new social infrastruc

Representation ID: 1496

Received: 08/09/2017

Respondent: IM Land

Agent: Turley Associates

Representation Summary:

Please refer to response to Question 28.

Attachments:

Comment

Black Country Core Strategy Issue and Option Report

Question 28 - Do you think physical infrastructure is necessary to serve large new housing developments? Yes/No; If yes, what type and scale of physical infrastructure is necessary?

Representation ID: 1497

Received: 08/09/2017

Respondent: IM Land

Agent: Turley Associates

Representation Summary:

Paragraph 5.7 of the I&O Report sets out that as options for the location of major new housing allocations develop through the review process, so will decisions about the need for any such facilities and their locations.

This approach will be necessary to understanding the full infrastructure requirements for new sites. As set out in response to Q2, the infrastructure assessments to be undertaken will be crucial in understanding these requirements further. This should also be informed by any site specific evidence base work undertaken by developers, as well as liaison with infrastructure providers (including statutory undertakers).

Attachments:

Comment

Black Country Core Strategy Issue and Option Report

Question 29 - Do you think there are any other tools or interventions that could be used to ensure enough infrastructure is provided by developments? Yes/No; If yes, please provide details.

Representation ID: 1498

Received: 08/09/2017

Respondent: IM Land

Agent: Turley Associates

Representation Summary:

As set out in response to Q2, the infrastructure assessment work to be undertaken by the authorities will be critical to informing what infrastructure will be necessary to unlock new development.

Attachments:

Need help completing this? Click here for our simple user guide.